The Task in hand!

Work on the overhaul of Austerity No9 started in June 2019. The blog was started in June 2021 so photos and text will be added as the work progressed through that period. Because of the Covid pandemic work was interupted during that time but the intention is to restore Austerity No9 to working condition as an N.C.B locomotive in blue. Work continues.............

12 September 2026

Grit blasting, protection and Christmas arrives early!

John Bratchell-Hunt sealed the footplate ends of the tank and blanking plates were made to cover the injector and balancing pipe openings to stop grit entering. The underside of the saddle tank was grit blasted on the 27th of August and moved indoors to 4 road.  2 coats of primer, 1 of grey undercoat and a finish top coat of gloss black was applied over the next 3 weeks to protect it. The rest of the tank will be done as soon as possible depending on the weather. Alan worked on making the ejector pipe assemblage which is taking a new path into the smokebox. The left-hand step had been bent during the inverting of the tank and was returned to its original position with some heat. 

Then this week (w/c 7th September) Santa made an early Christmas delivery with some parts for us to assemble! Firebox, smokebox, foundation ring etc.

LH plate back on with blanking plate.

 Nick grit blasting.

Underside of tank grit blasted.

1st coat of primer.
Finish top coat in black!

 
Alan soldering part of the ejector pipe. 

Part of the ejector pipe under the running board.

Left had step.

Christmas has come early!
 
Does what it says on the steel!

No 9's new firebox.

Another view of firebox.

Smokebox next to No 9.

Door blast plate and rings.

The tank will be turned over and grit blasted when the weather allows. It will be filled to check it is water tight. As soon as the other parts arrive I will post another update.  

 