The Task in hand!

Work on the overhaul of Austerity No9 started in June 2019. The blog was started in June 2021 so photos and text will be added as the work progressed through that period. Because of the Covid pandemic work was interupted during that time but the intention is to restore Austerity No9 to working condition as an N.C.B locomotive in blue. Work continues.............

27 November 2026

Ejector, Blast pipe and blower!

Only a week since the last post but lots happening! The ejector pipe to the cab has been installed with all the joints silver soldered. Other parts of the pipe in the smokebox needed bending and these were filled with molten wax to stop any distortion during this process. This needed melting out to silver solder the joints. (No video of it exiting the pipes - thankfully!) The blast pipe was lifted into place via the newly cut out chimney opening. The plates covering the cylinder block obstructed the positioning and needed to be altered. This was not possible in situ so they were removed and cut to size. A new blower ring has been made and a flange to connect it to the front tube plate has also being made and fitted for size. Excellent workmanship. Again thanks to all who help in No9's restoration.

Silver soldering one of the joints.

Ejector pipe looking to footplate.
 

Ejector pipe in cab.

Plate on cylinder block needs adjusting!

Blast pipe fitting. New blower ring on left.

Molten wax - not chocolate!

 

Ejector pipe bending. Filled with molten wax to stop distortion.

Supporting pipe for silver soldering.

Blower ring on top of support for spark arrestor on top of blast pipe. Sorry about strop in photo.

24 November 2026

Tank, chimney & steam pipe.

 On the 2nd of November the remainder of the saddle tank was shot blasted and 3 days later Murray Duncan primed it. It was then moved under cover onto 6 road until further work is done. The chimney, lying outside for a long time, was taken into the Shed and the old threaded studs burnt out. These had already been partly drilled out. Cleaned and tapped we inserted 7 bolts. Threaded studs will be used to fix it in position. As you can see from the picture a chunk has been knocked out which will required welding back in. It will also be shot blasted. Alan plasma cut the hole for the chimney in the smokebox, which had previously been marked out by Israel Newton & Sons Ltd. Video in that section of the Blog. The steam pipe, hidden in one of the wagons, was found eventually, and fitted in the smokebox along with the elbow to complete the puzzle! The end crinoline fixtures were salvaged to be used again and the straps were scrapped. Once more thank you to all who help in her restoration!

Preparing to shot blast the tank.

 
Alan doing part of the top.

Top finished.

Murray Duncan priming the tank on the 5th November.

Tank priming complete.

Chimney transport to Shed! Not easy over soft ground!

Old studs burnt out, holes tapped and 7 bolts inserted. 1 to go where the chunk is missing.

Steam pipe and elbow on tube plate.

Crinoline strap ends recovered. Crinoline straps scrapped.

30 October 2026

Tube plate to smokebox.

The remaining parts have been delivered from Israel Newton & Sons Ltd, riveting the smokebox front to the wrapper has been completed, along with the strengthening rings, and all the rivets are being ground flush. The front bracket has been trial fitted ready to be secured to the cylinder block, and the doubling plates riveted in place. To allow a trial fitting of the smokebox/tube plate it was secured in place by one bolt and some threaded rods.Two brackets to attach the tube plate to No 9 has been sourced, cut to size and drilled.  More drilling and riveting to follow. Thanks once more to all who help in her return to steam!

 

2nd delivery from Israel Newton & Sons Ltd

Front bracket attached for a trial fit. Bolted to cylinder block & smokebox front.
 
LH doubling plate getting riveted. 

Smokebox riveted! Superb work by Nathan & Doug Paul.

Dart bracket riveted - flat both sides.

Rivets being ground down on face. Jamback on chair.

Front tube plate in wrapper. Secured for a lift to the engine. See next photo.

Threaded rods securing the lower part.


Raising the smokebox/tube plate.

Trial fitting.

Front tube plate bracket measured - ready to be plasma cut.

Angle iron we cut from length and in half with many cutting discs!

11 October 2026

Smokebox assembly.

 A long post this time - but a lot completed. We are still waiting for the remaining parts from Israel Newton & sons Ltd (due to carrier issues) but lots of things are needing done before they arrive. The boiler barrel has been brought into the Shed on 1 road and Benny McInnes has been working on it. The smokebox front has had the 2 strengthening rings bolted on and that, and the wrapper. have been bolted together, and the holes countersunk for riveting. The doubling plates (smokebox side stiffeners) are now on (we found a plug from the Rotabroach drilling lodged between them - removed!). The saddle tank was inverted and filled with water and a small hole was discovered which has been patched. The rest still to be grit blasted - awaiting dry weather when we are on Shed! On Saturday 10th October the smokebox was trial fitted to No 9, and after some fettling is sitting nicely in place. The front bracket has been drilled to accommodate the bolts to the cylinder block casting. Steady and visible progress being made.

Both strengthening rings on smokebox plate. Door hinges on temporarily.
 
Firebox stored in wagon for the time being.

Holes drilled and bolted wrapper to front plate.

Rotabroach comes into its own on curve!

 LH doubling plate (smokebox side stiffener) clamped and partially bolted.

Boiler barrel on 1 road. Benny doing some remedial welding.

Barrel braced.

Benny's weld.

RH side of smokebox - all ready for riveting.

Trial fitting - nicely done!

Smokebox trial fitted. Front bracket can be seen and dart brackets. See next photo.

Front bracket - 5 holes drilled.
I'll not wait so long until the next posting! Again thanks to all who help in her restoration.

12 September 2026

Grit blasting, protection and Christmas arrives early!

John Bratchell-Hunt sealed the footplate ends of the tank and blanking plates were made to cover the injector and balancing pipe openings to stop grit entering. The underside of the saddle tank was grit blasted on the 27th of August and moved indoors to 4 road.  2 coats of primer, 1 of grey undercoat and a finish top coat of gloss black was applied over the next 3 weeks to protect it. The rest of the tank will be done as soon as possible depending on the weather. Alan worked on making the ejector pipe assemblage which is taking a new path into the smokebox. The left-hand step had been bent during the inverting of the tank and was returned to its original position with some heat. 

Then this week (w/c 7th September) Santa made an early Christmas delivery with some parts for us to assemble! Firebox, smokebox, foundation ring etc.

LH plate back on with blanking plate.

 Nick grit blasting.

Underside of tank grit blasted.

1st coat of primer.
Finish top coat in black!

 
Alan soldering part of the ejector pipe. 

Part of the ejector pipe under the running board.

Left had step.

Christmas has come early!
 
Does what it says on the steel!

No 9's new firebox.

Another view of firebox.

Smokebox next to No 9.

Door blast plate and rings.

The tank will be turned over and grit blasted when the weather allows. It will be filled to check it is water tight. As soon as the other parts arrive I will post another update.