The Task in hand!

Work on the overhaul of Austerity No9 started in June 2019. The blog was started in June 2021 so photos and text will be added as the work progressed through that period. Because of the Covid pandemic work was interupted during that time but the intention is to restore Austerity No9 to working condition as an N.C.B locomotive in blue. Work continues.............

3 November 2024

Paint, paint, axle boxes, slide bars & more paint!

 Another productive month with the inside frames getting a signal red finishing coat and the outside a 1st coat of NCB Midnight Blue. The brake cylinder, put back in place, will be fitted with the insulation and new cover.  Axle box trial fitting and the 8 slide bars was completed with lots of measuring for both, and shims being fitted. All the slide bars, along with their bolts, were all marked. This allowed for easier fitting. The front buffer beam has been removed to allow the boring of the cylinder(s) and this uncovered some areas needing cleaning. We don't know when this had been removed before (probably before arriving from NCB in 1976) but the bolts had been put back in the wrong way round!

Alan Coulson on the red!


Brake shaft in black.

Brake cylinder being lowered into place.

Brake cylinder back in place.

LH side front leading horn guide.

LH side front leading axle box in trial fit.

Trial shim. New ones will be aquired.

One of the original slide bars.

All 8 slide bars back in place. Adjustments and shims still to be made.

Buffer beam removed and cleaned.

All 6 springs ready to go back in. Pins all renewed by Robin Taylor.

Brian Warrender -1st coat of Midnight Blue 20C40. 2nd Nov '24


5 October 2024

A variety of new advances!

 Over the last month or so the remaining reaming to the frame and the springs etc has been completed and the reverser weighshaft has been returned to the frame. After trying to source new angle (26ft + long x 2) for the running board supports, the original ones have been repurposed, needlegunned, primed and undercoated. Brake rods have also been refurbed and are all in good condition. The brake cylinder, which we put back on the frame, had to be taken off to attach a cover for insulation. Robin Taylor has been making all the pins for the springs, the old ones were past their sell by date! Part of the inside of the frame has been given a 1st coat of signal red and looks great - another step forward. One other big step forward is the wheelsets have been sent to Riley's for re-tyring etc. They arrived there on Tuesday 1st October. Thanks to Nathan for getting that through!

Nick on lifting duties with the reverser weighshaft.



Weighshaft in place.

Another view of the weighshaft in place!

Angle supports for running boards in undercoat grey. 26ft 9".

The brake cylinder with cover for insulation purposes.

Spring, hanger and new pin. Marked to relate to both - 12.

3 sets of springs.

 The die tool repairing the damaged threads.

Brake rods with protective primer and grey undercoat.

Brian Warrender applying a coat of signal red to the inside frame.

Alan French checking out the new paint scheme.

Another view of the frame.

Wheelsets on lorry ready to go to Riley's.


30 August 2024

Brake shaft back in!

 A day to celebrate as the first major piece of the No 9 jigsaw is put back in place. The brake shaft was lanquishing in the shrubbery at the back of the Shed since its removal on the 3rd August last year. Needle gunned, primed, protected with a coat of light grey and greased up ready for its return to the frame, Alan Nick and I, with support from Rory on the telehandler, raised it up on the gantry and lowered it into place. Adjustments by podgers and the bolts were secured in place. The moment the shaft swung down on the bearings when I tightened the last nut was very pleasing and satisfying!


The brakeshaft bearing in the washer showing works number 7097 and NCB blue paint.

Nick steading the brake shaft as Alan lowers it into the frame. At this point it was the wrong way round and needed turning.


Adjustments with some podgers.

A couple of bolts in but still with support from the gantry.

The brake shaft has turned!

The reverser weigh shaft with one bearing that Robin made adjustments to.



Reaming in preparation for re-assmbly.

 The measuring continued and was completed successfully, including the axle boxes, allowing work to progress with their eventual refitting. The cylinder covers were examined and no "nasties" were found. Further cleaning, grit blasting, and painting took place and we moved on to reaming out all the holes in the frame, brake hangers, springs etc. With much appreciation from all of us Nathan produced a torque wrench with a multiplier to reduce the speed needed to reem out the 50 plus holes which was accomplished. Robin Taylor will make all the new pins as the existing ones were to say the least, loose. A couple of videos are available in this section to watch the reeming of both frame and springs.

A separate section will follow next on the re-installation of the brake shaft on the 29th August by Alan, Nick and myself, ably assisted by Rory on the Tele-handler.

Alan measuring the axle box.



No "nasties" found in the front cylinder box covers.

Cleaned out and ready for grit blasting and protecting.

Hand reaming was brutal and only 2 holes were achieved.

Reaming out spring hangers on the vertical drill.

Springs being reamed.- 15 on these alone.

Brake shaft and weight shaft needle gunned and primed. These were lying out side at the back of the Shed since being removed last August.

Cylinder and slide valve covers protected.



23 July 2024

 Bush removal and measuring!

The wasted studs in the cylinder block & blast pipe have been replaced and the frame has been given a protective coating of grey. We retrieved items from the wagon in preparation for grit blasting and painting although this has still to be done. Mud doors were checked to see if they need any work and a new mould will need to be made as they are different to the mould we have for other engines. The new stretcher & stiffener have been given a coat of primer and look good! The bushes have been pressed out from the coupling rods (with relative ease).  We installed dummy axles and the process of measuring the centres has begun. This will continue.........!

Some dry weather would allow us to grit blast all the larger parts - brake stretchers, weigh shaft, hangers and chimney out in the yard and get them protected and back under cover. Let's hope so.

Alan flushing out a wasted stud.




No 9's frame in protective grey protected by 9F and 5025!

Brake hangers ready for grit blasting.

New studs for blast pipe.

New studs in cylinder block.

Trial fitting of mud doors in what remains of No 9.

New stretcher & stiffener by John Hunt.

Pressing out bush.

Waiting to lift and turn the coupling rod. Levelling with 3 blocks and a bit of sterling board! (Nick's photo)

Alan measuring between the LL & LC dummy axles.


Dummy axle RC driving wheels.

One bush with uneven shape.

All bushes removed.

Chimney, weigh shaft and brake stretchers waiting for some TLC!